U3O8$86.00/lb0.62%|CCJ$121.082.31%|OKLO$74.444.12%|CEG$198.451.15%|URA$28.901.51%|URNM$52.302.84%|NXE$12.573.42%|U3O8$86.00/lb0.62%|CCJ$121.082.31%|OKLO$74.444.12%|CEG$198.451.15%|URA$28.901.51%|URNM$52.302.84%|NXE$12.573.42%|
SECOND ATOMIC AGE

Akkuyu NPP

Akkuyu Nuclear Power Plant in Turkey, a 4.8 GW VVER-1200 project built by Rosatom, with unit 1 grid-connected April 2024.

Four 1.2 GW AES-2006 reactors planned for completion by 2028, financed 60% by Russia via loan. First Russian-designed plant built abroad under BOO model. Supplies 10% of Turkey's electricity.

Why it matters now

Highlights Rosatom's export dominance despite sanctions, contrasting with Western SMR licensing delays; relevant for 2025 supply chain risks in VVER fuel.

Related reactors

VVER-1200

Sources

  • World Nuclear Association: Akkuyu NPP
  • Rosatom Press Release on Akkuyu Unit 1

Last reviewed: about 16 hours ago·Status: published